Can Dominion Be Made To Stand Behind Promises?

Perhaps the biggest weather risk to the performance of Dominion’s planned offshore wind project. In all the briefs about mitigating risk, the word hurricane appears once.

by Steve Haner

First published this morning by the Thomas Jefferson Institute for Public Policy. Second of two articles.

In promoting its proposed Coastal Virginia Offshore Wind (CVOW) project, Dominion Energy Virginia has made many specific projections about its costs and performance. The State Corporation Commission is now being advised to convert one or more of them into binding promises, with financial consequences for the utility and its shareholders if the 176 turbines fail to meet expectations.

As noted in previous discussions, including part one yesterday, Dominion’s 2.6 million Virginia customers are fully exposed to any additional costs created if the construction schedule falters, if material costs explode, tax credits disappear, or if the amount of energy provided over the next 25-30 years fails to meet targets. As also previously reported, no other similar project on the U.S. East Coast is structured to put full risk on customers.

Virginia’s General Assembly created it that way. Many of the groups now offering advice on protecting consumers were supporting the bill at the time. But under the “better late than never” rule, their ideas now are worth exploring. The Commission had asked for this advice and got several responses in briefs filed June 24.

The most common suggestion is to create a performance guarantee built around what is called the capacity factor. Even the best power plants do not operate at full capacity 24/7/365. The actual power output divided by the full output potential produces a percentage “capacity factor.” In its application and in hearing testimony, Dominion stated its two-turbine CVOW demonstration project achieved a 47% capacity factor. For this much larger project and longer time period the company projected 42%.

Make that mean something, put some teeth behind that, advised the Consumer Counsel to Attorney General Jason Miyares, a coalition of environmental groups who filed as a team, Clean Virginia and retail giant Walmart. Wrote a member of Miyares’ staff on his behalf:

Consumer Counsel recommends that for the life of the CVOW Project’s commercial operation and beginning three years after February 4, 2027, customers be held harmless from any incremental cost and diminished benefit incurred due to any shortfall in energy production (and associated tax credits and renewable energy certificates) below an annual net capacity factor of 42% based on the CVOW Project’s combined nominal capacity rating of 2,587 MW (AC), with reasonable adjustment for energy losses, and as calculated on a three-year rolling average basis.

From Walmart, after recounting all the promises in Dominion’s paper filings and testimony, all under oath:

These representations by the Company should be more than words on paper, but a promised level of future performance that customers can rely upon. A performance guarantee provides that promise to customers, and it helps mitigate the risks of both construction and ultimate project performance. Accordingly, for the life of CVOW’s commercial operation and beginning three years after February 4, 2027, the anticipated date for the last turbine installation, the Commission should impose a performance guarantee based on a 42 percent capacity factor as calculated on a three-year rolling average.

In testimony filed by the SCC staff, also charged with thinking about consumer protection, a similar provision was proposed but at a lower capacity factor, more than 10% lower. It suggested financial consequences if capacity drops below 37% over a sustained period of time. In urging rejection of that low performance mandate, Walmart noted:

This (staff) proposal is based on the absolute lowest potential capacity factor modeled by Dominion in its levelized cost of energy analysis (38%), discounted further based on the estimated turbine availability factor.

A requirement for a 37% capacity factor rather than 42% represents about 3,000 megawatt hours (MWh) less guaranteed power production per day, 1.1 million MWh less per year, and about 28 million MWh less over the 25-year life of the project. Even if Dominion builds the project on budget, the lost value of 30 million megawatts of output is measured in billions of dollars.

The “availability factor” mentioned above measures how often during that 24/7/365 year of service some or more of the turbines are offline due to maintenance or equipment issues. Dominion’s promise there is 97% over all those years, something else that could be tied to a performance requirement.

Despite its own suggestion, the staff of the State Corporation Commission signed a stipulation with Dominion Energy and backed off a hard performance guarantee. It agreed that it would be sufficient to make the company report cost overruns or performance failings and then let the Commission deal with them at the time. Here is the staff’s brief. No firm performance guarantee is in the stipulation, which the Attorney General and environment respondents did not sign.

The other frequent (but less unanimous) suggestion was to try to place a hard cap on the construction costs for the turbines and related transmission lines, onshore and off. Dominion’s official cost projection has ticked down to about $9.65 billion, which includes a $300 million contingency and allowances for currency fluctuations.

The problem here is that long-standing utility law promises investors will recoup their reasonable and prudent expenses, and it is already the case that cost overruns (if any) will have to come to the Commission for review and approval. Legally it is unlikely the SCC could force the company to eat construction cost overruns.

Will the Commission kill a project over costs once construction is well advanced? Unlikely. More practical are suggestions that the SCC set some hard requirements that Dominion immediately report setbacks or issues. The stipulation doesn’t do that. But if the bad news comes quickly enough, perhaps the Commission could pull the plug.

From the environmental respondents’ joint brief:

The V.C. Summer nuclear debacle is a cautionary tale. There, even after South Carolina Electric & Gas (“SCE&G”) abandoned the project, it still claimed it could charge its customers about $3.33 billion in unrecovered construction costs. Even after Dominion sweetened the pot with various adjustments, South Carolinians are still paying roughly $2.77 billion for a project that will never deliver them a single kilowatt of electricity. Had the South Carolina Commission forced SCE&G into abandoning the project earlier (by denying recovery of unreasonable cost overruns), it could have saved ratepayers billions of dollars. Ratepayers deserve mandatory, rapid review of cost overruns, which Dominion refuses to give them in this case.

In its 95-page brief (about the length of three others combined) Dominion fiercely resisted a firm guarantee built upon the capacity factor, whether 42% or the lower 37%. It claimed the reporting requirements in the stipulation are sufficient and the SCC can deal with setbacks if and when they arise. It wrote:

As noted in the evidence, capacity factors (defined as the percentage of hours in the year of actual generation by the Project) for a wind or solar facility are influenced significantly by the weather. While the Company believes that the projected capacity factor for the Project is well-grounded and reasonable, future weather patterns, as well as certain other operational factors obviously are beyond the Company’s control. Any average capacity factor projection is also on a “life of facility” basis, which will vary annually…

Well, exactly. That is the risk in a nutshell. Sometimes there is no wind and sometimes too much. (A word search of all briefs found one mention of hurricanes, in the staff document.) But Dominion dismissed the proposals to shift the costs away from consumers:

… In terms of the calls for “doing more” in order to mitigate risk for customers, there is simply an absence of substantive recommendations and associated evidence in the record, beyond the terms of the Stipulation, which are permissible, appropriate, and justified for this Project.

As noted in the previous column, the real question is what steps two judges will take faced with a legislative mandate that showed no concern for ratepayer risk, reinforced by the defeat of a reform bill earlier this year? Will it do what the General Assembly refused to do?


Share this article



ADVERTISEMENT

(comments below)



ADVERTISEMENT

(comments below)


Comments

31 responses to “Can Dominion Be Made To Stand Behind Promises?”

  1. Dominion’s argument in a nutshell: Let us build the offshore wind farm, give us a guaranteed return on investment, but don’t hold us accountable for the risk that the weather might not cooperate.

    Sweet deal if you can swing it.

    1. LarrytheG Avatar
      LarrytheG

      Done deal already, no?

  2. Turbine availability risk can likely be pushed back to Siemens (for a while at least). I keep pointing towards the georgia nuke plant debacle as the perfect example of construction and technical risk. While a wind farm is not nearly the same as a design-build nuke plant project, there are plenty of opportunities for overruns. For example, foundation-related problems can occur if the seabed ends up being different than expected.

    I am probably on an island here, but to me, this issue is more about Dominion not wanting to accept any risk than it is about OSW itself.

    If Dominion doesn’t want to accept the weather risk, i.e., capacity factor guarantees, then is it possible to make them provide the shortfall at market costs. IOW, whatever power they have to backfill during a less windy year has to be done at prices commensurate with normal baseload generation; not peaking plant prices.

    1. LarrytheG Avatar
      LarrytheG

      Yes. Imagine if Dom wanted to put a 3rd Nuke at North Anna. Who do you think would carry the risk – shareholders? hahahah bahahahahah

    2. Stephen Haner Avatar
      Stephen Haner

      Yes, there are some warranties for a while but again, redacted I suspect and thus secret. I am no cheerleader for OSW but it would be better if we were working with a third-party developer as so many other states are. The reasons we are not are all bad.

      Some of the briefs point out that this is just Phase 1. Dominion was planning Phase 2 long before Biden made it a national priority. The Assembly COULD insist that Phase 2, if done, have a very different risk profile. But too late for Phase 1 and the 2031 superstorm will take them both out. 🙂

  3. James Wyatt Whitehead Avatar
    James Wyatt Whitehead

    Tomorrow we can wish Dominion’s two turbines installed a happy second birthday. Do they work? What is the assessment of the Dutch powered behemoths?
    https://dailyenergyinsider.com/news/26145-dominion-energy-installs-2-turbines-for-the-coastal-virginia-offshore-wind/

  4. James Kiser Avatar
    James Kiser

    Interesting on my travels through Kansas (6/22) the number of wind turbines I saw that were non operational due to missing blades. I would estimate that 1/3 were missing 1 or more blades due to the bad weather that was recently experienced. I also saw a number of trucks transporting replacement blades as well as a large number of trucks transporting electrical transmission equipment. Where would you find info on the damage and outages in the midwest?

    1. Stephen Haner Avatar
      Stephen Haner

      Not sure who reports what to whom but utilities do report on power output from their generation assets, so those will dip under those circumstances. There is a small offshore wind facility off Rhode Island that was down for weeks and weeks in 2021 with similar issues. It happens. The promised 97% “availability” factor is…aggressive.

      1. James Kiser Avatar
        James Kiser

        I meant to mention that beside the windmills missing blades that another 30 % or so were not not working even though other windmills near them were turning and there was a steady wind.

  5. f/k/a_tmtfairfax Avatar
    f/k/a_tmtfairfax

    If something is available only 30-some to 40-some percent of the time, it’s wrong to charge captive customers 100% of the costs. Based on 40 plus years of dealing with utility and common carrier regulation, there is no way that any PUC should approve placing 100% of the investment and expenses on ratepayers. In the event that a higher percentage of the risk goes to ratepayers, Dominion’s business risk is reduced substantially. Under accepted principles of regulatory law, a utility’s rate of return is based, in large part, on its financial risk (debt vs. equity) and business risk. When the latter goes now substantially, so should Dominion’s allowed rate of return.

    Dominion has a fairly large footprint for electricity in NE NC, fortunately not where I live. It also provides natural gas service in part of the state, including Wake Forest. So far, no complaints on that side.

    1. capacity factor is effectively the percentage of the rated capacity that is delivered. It’s never 100% because of planned or unplanned maintenance or whatever, but nukes are by far the highest in the 90s. The average capacity factor in the US for coal and gas plants is 50% and 55% respectively.

      Should we recoup investment for the coal and gas plants not running at 100%?

  6. LarrytheG Avatar
    LarrytheG

    there are more than 70,000 wind turbines in the US. No, they’re not quite the same as offshore but the point is they have had significant experience with reliability, longevity and weather:

    https://uploads.disquscdn.com/images/334ce2a05cd9c883a98492a6752a24d370ae52ef1390f8ed4e402f0a85703e02.jpg

    https://eerscmap.usgs.gov/uswtdb/viewer/#3/37.25/-96.25

    there are more than 3000 wind turbines in the North Sea:

    https://uploads.disquscdn.com/images/2c7703e078c5ad65afaf33451fb54b3ad264a7ea065120f6942b208a644dd9d7.jpg

    https://northsearegion.eu/northsee/e-energy/offshore-renewable-energy-developments-offshore-wind/

  7. Eric the half a troll Avatar
    Eric the half a troll

    I have no issue with the risk being partially shifted to stockholders (which is the only other alternative available to users). If this were a true public utility the two alternatives would be users or taxpayers. Are you sure you want the burden shifted to retiree’s 401k accounts? I will not again that those with distributed generation are the ones most protected from these sort of cost overruns.

  8. energyNOW_Fan Avatar
    energyNOW_Fan

    I’ll be shocked if we get any openness on performance of the plant after completion. Presumably efficiency will deteriorate as the blades experience erosion due to weather etc.

  9. LarrytheG Avatar
    LarrytheG

    Maybe I don’t understand, but if this is already a done deal signed off by the GA, why would Dominion want to agree to anything that would increase their downsides?

    And also, with prior capital projects , like Coal and Nukes, was Dominion held to a standard similar to what is being advocated now?

    Third – why is Youngkin seemingly not on board with this?

  10. James C. Sherlock Avatar
    James C. Sherlock

    Regulated utilities are supposed to offer assurances of service 24/365 in return for assured profits at rates controlled in advance by the state. Regulated utilities are artifacts of the government trading monopoly for customer service reliability.

    Wind farms do not offer the assurance of uninterrupted energy. That means something must give, profits or rates.

    That brings into question why a regulated utility is allowed to go in to the wind and solar businesses. Those are investments better fit for unregulated utilities that sell power to regulated utilities when they have it to sell. Higher risk, higher reward.

    Virginia at some point decided that green energy needed to come before that approach and they wanted Dominion in the game. This is the problem that has created.

    1. I’ll disagree and say that it’s in the interest of the utility to have a diversity of energy resources in order to deliver the energy required at the price allowed. Russia has underscored the need for a broad energy portfolio for Europe with tight gas supplies. Plus, natural gas is transport constrained fuel. No pipeline, no fuel. Broken pipeline, no fuel. No wind, no electricity from wind….. Point is that no resource is perfect and no resource is permanent. Natural gas has made coal plants uneconomic and coal capacity is being shut down left and right as a result. Something has to replace that capacity.

      1. energyNOW_Fan Avatar
        energyNOW_Fan

        we do not really have an elec power shortage. We have that favorable profit guarantee policy and green subsidies that make it attractive for monopoly utilities, suppliers, investors to build out new plants as fast as they can right now.

        1. no argument there

      2. LarrytheG Avatar
        LarrytheG

        All these decades, Dominion has used a diversified mix of energy sources to deliver reliable power 24/7 per their monopoly agreement.

        Why now, are the naysayers and climate deniers “concerned” about it?

      3. James C. Sherlock Avatar
        James C. Sherlock

        Nuclear. Meets the reliability standard for a regulated utility. Look at France. And newer nuclear power systems are much safer and produce little waste.

        My point is that private utilities should be encouraged to invest in solar and wind, not regulated utilities. That could be done by directing the regulated utilities to buy increasing amount of green energy from private utilities over the years as technologies advanced. Then permit the regulated utilities to create private subsidiaries to compete in that market if they wished, but at their own risk. They would do it.

        1. Point taken on private vs regulated. We differ on whether wind can be included as a baseload resource.

          Nuclear is dead for now. No utility in US will dare try to build one.Unless you want the Chinese, Russians, or Indians being in responsible for your nuclear energy infrastructure.

          1. James C. Sherlock Avatar
            James C. Sherlock

            Thanks, good discussion.

    2. I’ll disagree and say that it’s in the interest of the utility to have a diversity of energy resources in order to deliver the energy required at the price allowed. Russia has underscored the need for a broad energy portfolio for Europe with tight gas supplies. Plus, natural gas is transport constrained fuel. No pipeline, no fuel. Broken pipeline, no fuel. No wind, no electricity from wind….. Point is that no resource is perfect and no resource is permanent. Natural gas has made coal plants uneconomic and coal capacity is being shut down left and right as a result. Something has to replace that capacity.

    3. LarrytheG Avatar
      LarrytheG

      The deal with the monopoly is that they provide the power and they decide how to do that.

      You don’t get to question how they do it.

      If they want to use an energy source that is not available 24/7 but when it IS available , it’s cheaper – and they can successfully “blend” the sources to deliver reliable 24/7 power – then why would you question it? Did you question it when they used coal and nukes with hydro?

      1. James C. Sherlock Avatar
        James C. Sherlock

        See my reply to ARL. “You don’t get to question how they do it” is simply not true, Larry. That is what the “regulated” part of a regulated utility means.

        1. LarrytheG Avatar
          LarrytheG

          the agreement is to supply reliable power 24/7 in exchange for the monopoly.

          If they deliver the goods – they’re met the terms of the agreement. They’ve delivered the contracted goods.

          How they do it is not your business. In fact when something goes out for bid – how competitors will provide the goods is proprietary information.

          It was not your business when Dom did coal plants and piled up ash waste that we paid extras for later nor when they built a nuke on an earthquake fault or really anything else as long as they meet the terms of the agreement.

          It’s actually the same when the govt contracts with other private sector companies – I’m sure you dealt with this in your career – It’s called ‘deliverables” and you don’t get to specify how they do the work though I do recall we were allowed to see the credentials of those that would be hired.

          Finally, it would be the same thing with a private sector provider of wind/solar. They sign an agreement to deliver specified product/services, you don’t get to tell them how to do it. In fact, that’s one of the benefits of hiring the private sector – they will find more efficient ways to do the job than the govt would.

  11. A multi-billion dollar cliffhanger! Gotta laugh at the “lifetime capacity factor”. They could run low for ten years or more with no penalty, saying “just wait”.

  12. WayneS Avatar

    My suggestion:

    Require Dominion to guarantee a Capacity Factor of 45% and Availability Factor of 95% , with stipulated penalties for each percentage below the guaranteed value. Each of the above values is two percentage points below Dominions claimed performance level for the project, so they should have no problem meeting them.

    During the life-cycle of the project, use a three-year rolling average of CF and AF for purposes of measuring performance. This means the possibility of penalties is in play from Year Three on.

    At the end of the life cycle compute the Lifetime CF and Lifetime AF, assessing additional stipulated penalties for each percentage point, or part thereof, the Lifetime values fall below the guarantee.

  13. energyNOW_Fan Avatar
    energyNOW_Fan

    Mad Money with Jim Cramer last nite, Cramer was talking about how the current inflation/probable recession scenario is stopping rampant financial speculation. However, I suggest that is for private industry. Utilities can forge ahead with their green speculation since they are guaranteed to profit handsomely (public has to pay the cost) even if the project(s) is/are a huge failure.

Leave a Reply