Show Me the Money

 

With transportation funds tight, the Warner administration is turning to public-private partnerships to build new highways. But critics worry that low-priority projects are moving to the front of the line.

 

By Bob Burke

 

When backers of a $900 million plan to build high-occupancy toll lanes on the Capital Beltway came to Richmond last year hoping to close the deal, the message from Philip Shucet was: Show me the money.

 

California-based Fluor Enterprises was pushing a proposal that needed no state funding, using tolls to cover the debt, but involved no investment by Fluor. “I remember bringing the Fluor folks in, with nobody but in the room but me, and saying, ‘I like this project, but I’m not sure I want to move it forward,’” says Shucet, who was then commissioner of the Virginia Department of Transportation.

 

What was missing, Shucet told them, was any financial risk by the private side. So Fluor came back with a new partner, Australian firm Transurban, which agreed to invest at least 15 percent of the project’s total cost. “What that told me was if someone was willing to bring capital to the table, then this must be a good business deal,” he says.

 

Shucet calls the Beltway deal “a turning point” for VDOT, because the infusion of private-sector money reversed a trend. Virtually all previous projects done under the state’s 1995 Public Private Transportation Act (PPTA) “were basically sole-source deals to spend state and federal revenue,” he says. “There wasn’t much of a private side at all.”

 

Today, that kind of private-sector risk-taking is what VDOT and state leaders hope to see more of. Cash- strapped Virginia is already aggressively pursuing private partnerships to help advance major projects. Besides the Beltway lanes, Fluor and Transurban have proposed extending HOT lanes down the Interstate 95 corridor to near Fredericksburg. Other active PPTA proposals include extending Dulles rail, widening Interstate 81 and building a third crossing in Hampton Roads.

 

These kinds of partnerships are changing how Virginia pays for transportation projects – with more tolls and special tax districts likely - as well how it decides which ones to build. Exactly what that means for the state’s transportation network is still uncertain.

 

Supporters like the infusion of private-sector expertise and cash – especially the cash - but others worry that the state is turning over too much control to profit-oriented businesses.

 

“The PPTA is still not integrated very well with our normal transportation planning process,” says Trip Pollard, an attorney with the Charlottesville-based Southern Environmental Law Center, which produced a study of the PPTA in January. “You want to tap into the creativeness of the private sector, but you also want to be sure that you’re harnessing those market forces toward serving the public interest.”

 

Virginia’s current approach to harnessing that market is to spur it along. State legislators this year created the Transportation Partnership Opportunity Fund, which allows no-interest loans or grants to support transportation projects through the PPTA or the design-build approach.

 

The fund, which has $50 million this year, will be used to give some early financial stability to public-private projects, says Secretary of Transportation Pierce Homer. As funding sources, tolls and tax districts “take longer to mature,” he says. Such was the case with the Route 28 Tax District in Northern Virginia, which was created in 1988 but took years to meet its initial revenue projections. Or the Pocahontas Parkway, a toll road southeast of Richmond that opened in 2002 and soon fell far short of traffic projections. The Pocahontas Parkway Association is negotiating a sale of its toll road business to Transurban.

 

 

Pocahontas Parkway, southeast of Richmond,

when under construction.

 

“A lot of the focus of this new fund will be to help private entities build private markets,” Homer says. “”By lowering the initial cost of financing, it will give a private entity a little more breathing room and the ability to develop that market.”

 

There are also new guidelines issued last month for the PPTA. The state now can sign interim agreements to give companies bringing proposals to VDOT some assurance that, if the project gets a green light, they’ll get the work. That lets both sides continue planning and evaluating a project, Homer says. Private firms “are not going to undertake that kind of thing unless they know they’re first in line.”

 

The guidelines also call for giving companies a quicker response when they submit unsolicited proposals to VDOT. Within 30 days VDOT has to start an initial review of the proposal to see if it meets “the planning goals of the commonwealth,” Homer says. “What’s important to the private sector is predictability.”

 

Homer says the new guidelines also promote more public review of proposals and to encourage competition, something state leaders have been working on for years. “In 2002 we sent back every PPTA proposal we got, and beat the bushes for competition” from other firms, he says. Counter- proposals came for projects such as the widening of I-81 and HOT lanes down the I-95 corridor. “Each step of the way we’ve brought new people into the fold.”

 

But critics warn against depending on market forces to make the right choices. The guidelines require that proposed projects “support and promote” the goals of the relevant state or local transportation plan, but that’s no guarantee, says SELC’s Pollard. “I don’t think the Pocahontas Parkway would have gotten to the top of the list,” he says. Instead of congestion relief and improved mobility, the roads that get built will not only allow sprawl, but encourage it, he says. “The proponents tend to have a vested interest in promoting rapid growth, because they want to have the toll [revenues] come out of it.”

 

Proponents acknowledge the impact on the state’s list of top projects, but say it’s better than nothing. “Wouldn’t you want to advance [a project] that someone else was willing to pay for?” asks Jeffrey C. Southard, executive vice president of the Virginia Transportation Construction Alliance and a former senior staffer at VDOT. “If the private sector’s willing to pay for number nine, why would we say, ‘Sorry, we’re only interested if you’re willing to do number one or number two.’”

 

Says Homer: “What we need to do is figure out which of our priority projects is best served through the PPTA process” and direct the others to the traditional approach.

 

Of course, if the state had more money, its top transportation projects wouldn’t have to wait for an interested private-sector suitor. Southard points to another problem with the state’s budget problems: Even in public-private deals, the lack of state dollars is limiting what private firms can do.

 

“There’s relatively few PPTA projects that could pay for themselves entirely by tolls because the cost of construction is so great,” he says. Private firms are generating innovative ideas, but “the unfortunate thing is that in many cases, they’re having to revise their ideas because they know VDOT has no money.” 

 

The money issue is a long way from being resolved, but Homer and others think the state’s public-private strategy will succeed. “We are by any measure making great strides and trying to do it in a very deliberate fashion. We’ve created a very competitive framework,” says Homer. “I think we’re the best in the country right now."

 